Monday, November 16, 2009

Blog slap!

I have been blog slapped a few times for being so far behind!!
I will do my best to do some catching up on where things are at so stay tuned.

In short we had handover, we organised our own trades, we moved in, worked like animals for the past 3 months and just had maintenance.

A detailed update and photos are coming.

Thursday, July 2, 2009

Our fence has been put on hold.

The fence people arranged by the developer rang and said they have placed our job on hold because the site fences from the properties either side of us are in the way. The dirt from the left block site scrap is also in the way.
I rang SS and he will get rid of the fences from the next door PD site. I offered to chase up the other site for him since I already know the site supervisor from the Henley Home. I rang the Henley homes SS and he said he will get it remove A.S.A.P. and I also organised for the extra dirt on his site to be dumped in the lower part of our block to level it for us. It's a win win really, we get a level block and they get rid of the dirt.

I also rang E&S trading regarding our spa, they said it won't be ready by the 10th and I went ballistic. I spoke to the manager and tore his head off saying that I gave the require 3 weeks plus an extra week and that I will not accept it not being there on the 10th of July. He said he will pull some strings and get it there. He will ring me tomorrow to confirm.

Wednesday, July 1, 2009

Finance organised.

I arranged the final payment today and all is under control.

I also spoke to SS about the sid egate and he gave me some usful advice regarding the limited space. I think I will look for someonce else to do the gate. I also mentioned that the front garage lights are not evenly spaced in front of the roller door and he will get that fixed.

Tuesday, June 30, 2009

Gate quote.

I arranged to get a quote for the front and side gate. I seemed to get nowhere fast, there were issues with finding space for the side gate and I couldn't see anything in the photos of the work done that was what I was looking for. So I guess we have to look for other gate fitters.

Monday, June 29, 2009

Final touch ups

I met with an interior designer today regarding our choice of fabric for the drapes, I was not convinced with our original colour choice it seemed to clash with the shade of paint. I drove out to the site with the new fabrics and I am much happier with the new selection.

The painters are back patching and repainting walls. The front door has been varnish and the colour of the stain is perfect.

Sunday, June 28, 2009

What a weekend.

Today we went back to continue the work we began yesterday. Martin leveled the land on the blind side of the house and we then leveled the front together. We cleared the front building rubble spilling over from next door and put the site fence back up. We laid gravel between our house and next doors garage but we did not continue down the length of the house. We will wait until the fence up and then finish the job.

Martin then began moving the whole pallet of bricks out the front in our driveway to the back of the house. I helped as much as I could but I was limited in how much I could do with the boys now completely over it. I don't blame them poor kids have been bored out of their minds all weekend, sometimes I feel it's not fair on them but what can we do. We had been at the site all day and it was now 6pm. We were all tired, starving and grumpy so we did a "maccas" run on the way home before collapsing into our beds.

What a weekend!

Saturday, June 27, 2009

What a big job.

The truck driver from Midway arrived with our mountain of gravel. He was very careful not to drive over the pegs marked for the slab on next doors block. He was kind enough to dump the crushed rock in two places to make it easy for us to distribute.

Martin leveled the dirt and luckily it wasn't muddy or the job would have been a nightmare. Oscar was a pest and kept getting in Daddy's way while Daniel was a great help with is bucket and little spade. I had the wonderful job of raking the gravel out and leveling it.

We worked until dark and by the end of the day we were exhausted. We managed to to level and lay the gravel out from the back of the garage all the way to the end of the house.

Friday, June 26, 2009

Practical Completion Inspection

We had our P.C.I today and when we turned up at the sight we were horrified to see a site fence up on the house next door to our left. We were planning to get almost 5 cubic meters of crushed rock delivered and did not fancy having to cart over 50 wheelbarrows up a steep drive way. Our SS said he thinks it is a Henley home and suggested we ring them find out who the supervisor is and get access to the site this weekend before they get the plumbing and form work in. It is good of him to allow us to do this before handover.

The inspection went quite well most of the major stuff is done and there is just the finishing touches to be done. We went through the house with him putting spots on the walls where we want the painting patched due to damage by other trades. The house looked like it had measles when we finished.

The scratches in the bath have disappeared, all the kitchen cabinets are now correct. The alfresco beams look so much better now very impressed. The brick piers look much better and all the quads are now level.

We are looking at the 10 of July for hand over if everything has been complete ted.

When we finished our P.C.I. we had a concreter meet us for a quote he seemed helpful and reasonably priced so we are more than likely going to use him.

When we got home we managed to get in contact with the Site super for next door and he allowed us access to his site so that the truck can dump the crushed rock in our back yard. We rang "midway building supplies" as they are cheap and great to deal with. We organised for four and half cubic meters of crushed rock to be delivered on the Saturday.

Unfortunately we found out it is a double story going up next door. Grrrrrrrrrrr at least there is 6meters between us and them.

Thursday, June 25, 2009

Painter back again

The painter has been back to paint the patched up walls the plasterer made plumb also the bulkhead and cornice are now completed in the kitchen.

Wednesday, June 24, 2009

Carpenter back on site.

Quads at the front of the home have all been made level and the master window has been replaced. The alfresco beams have been covered in cement sheeting and the appearance is a vast improvement to the beams and uneven bricks. The pantry and laundry cupboards have been installed and the scratches in bath tub polished out.

Tuesday, June 23, 2009

Take 3

The master bedroom window has been delivered to site. This is the third window for the master bedroom, the first was too big the second was out of square and now we are hoping for third time lucky.

Monday, June 22, 2009

Bricks relaid

I spoke to SS and he said that the brick piers have been relaid again and that the new master bedroom window is being delivered tomorrow. The kitchen cabinet doors above the fridge have been replaced with a single door.

I mentioned the bath tub has been scratched and that the flood lights are wrong. We are still on track for the PCI (practical completion inspection) on Friday.

Saturday, June 20, 2009

Tiling to kitchen completed.

The tile layer returned and completed the tiling up the wall behind the rangehood, it looks fantastic.

We picked up the intercom unit for our home, we are installing the genie system 3 to have a basic intercom system. It is a small and compact unit not those big ugly bulky systems.

Friday, June 19, 2009

Site open

Tiles returned to site for the tile layer coming backing tomorrow.

I had a measure and quote done for the curtains.

The house has been cleaned and I noticed the bath has been scratched.

Tuesday, June 16, 2009

More progress.

The telephone line has been run to the property so we can now apply for a connection. The spot lights have been installed at the front of the property but they are incorrect. They have installed para flood lights and they should have installed magneto sensor spotlights.

The taps, shower heads, toilets have been fitted. The replacement alfresco door has been delivered to sit. The 4 door kitchen cabinets have also been returned to site to be fitted in the pantry and laundry but the handles are missing.

Monday, June 15, 2009

Arrangements.

Spoke to tile layer he is flat out and will come on Saturday to finish the tiling.

Rang SS let him know we left the tiles in the alfresco but he can not make it to site as his car has packed up. We will go back and pick up tiles before they walk off site and return them on Friday. We discussed the alfresco bricks, tiling, quote for the fence repair and also for the site to be open on Friday for the curtain quote.

Sunday, June 14, 2009

Weekend work.

We returned the kitchen feature tiles to site for the tile layer to complete the tiling at the rangehood now that the cabinets have been replaced. We noticed the cornice above the rangehood has been finished, they must be working weekends now.

We noticed a few bricks near the window at the alfresco are leaning, I will contact SS and let him know.

Saturday, June 13, 2009

Painting continues

The alfresco door has been varnished and looks fantastic, it must have just been done this morning.

Friday, June 12, 2009

One step forward two steps........

The correct 3 door kitchen cabinets have been fitted replacing the incorrect 4 door cabinets to be relocated. The only problem is that they are now missing in action! The incorrect two door cabinet above the fridge is also yet to be replaced.

Another site clean has taken place if it could be called that, with the recent rain we just had it has ended up looking more like a mud pit. The temporary fence and site toilet has been removed. The back fence between our property and the one behind us has been damaged, it looks like the bulldozer slid in the mud. I have contacted SS and reported the damage.

Thursday, June 11, 2009

Progress in the kitchen

The new kitchen sink has been installed and the pantry shelving has also been fitted, they left out the top shelf to fit the kitchen cabinets to be replaced. All the wardrobes have been fitted out as well.

Wednesday, June 10, 2009

The cost of curtains is outrageous.

We have got some quotes back on curtains and they are just outrageous. We are going to do some more shopping around. When I get a chance I will update with photos of the fabrics we like.

We are also getting quotes from carpenters to raise our alfresco floor and construct the frame work around our spa. The estimated quotes here are not fantastic either, I can feel a DIY coming on.

Monday, June 8, 2009

Extra long weekend????

Not much if anything at all happened on Friday, they must have all decided to have an extra long weekend.

We went on site today and moved the bricks that were in the middle of the building rubble. When they do the site clean the bricks would just get turfed. There is still a large pallet of bricks in the driveway which we have to move.

We found some concretors from another near by site in our garage trying to shield themselves from the icy winds while having lunch. I don't think they expected someone to turn up on a public holiday. They were good value because we got the name of a friend of theirs that concretes driveways.

Special thanks to Janine for watching our boys and Viv for helping us move the bricks.

Thursday, June 4, 2009

More fit outs.

The internal hangers and shelving in the wardrobes have been fitted. The shelving in the pantry has also been fitted leaving space for the cupboard being installed above the sink.

The new kitchen sink has also been installed as the old one walked off site.

The top four door cabinets in the kitchen have been replaced with three door units. They were supposed to be installed in the laundry and pantry but have been incorrectly removed from site. I have spoken to SS and he said they will be returned next week and installed.

There are a few errors with the electrical, there are para floodlights out the front of the property and there should be small ones with sensors. The master bedroom dimmer switch is in the wrong spot and the kitchen down lights are off centre. We are going to go back with our electrical drawings check the remaining electrical fit out.

Wednesday, June 3, 2009

Aircon in!

The refrigerated air is being installed today and the installer rang me today to ask where we want the unit. He saw that there is a power point in the rumpus for a projector and said he is moving the air conditioning vent in that room so that it won't interfere with the equipment. He is also putting the thermostat where we want.

The electrician was on site again today installing all the lights.

Tuesday, June 2, 2009

Site meeting with SS and sparky on site.

We met SS out on site today to go through the list of defects. The major issues have been resolved and we have now agreed to make payment on the fixing invoice.

Fixed:
  • The brick sills and front step all relaid without split bricks.
  • Pier at portico bricks now straight.
  • Cement sheet leveled above meter box.
  • Fascia fitted closer to the walls removing gaps.
  • Gutter at alfresco fixed.
  • Roof tiles over master bedroom fitted properly.
  • Bow removed from kitchen wall.
  • Master bedroom window above bed has had trimmer installed.
  • Flashing to alfresco door and front door installed.
  • Front door replaced.
  • Entry door quirk now level
  • Garage door now level and plumb
  • Toilet window now in the center.

Outstanding:
  • Brick piers at left and right of garage to still be straightened.
  • Mortar blow outs to be filled.
  • Windows, repair dents (dining, rumpus, toilet), replace vinyls, fit aluminum angle to toilet window and replace front master bedroom window as the right hand small windows are not square.
  • Quads still to be made level at front of house, quads will be replaced at alfresco with a wider quad and end beam will get covered in with cement sheet as it is rough.
  • Front fascia over garage to be replaced, portico gutter to be replaced and study fascia to be adjusted.
  • Fix reinforcement to dishwasher space for stone.
  • Bottom of wall at games room still not plumb
  • Flashing at laundry door will be removed and caulked instead.
  • Sand and repaint bulkhead at entrance.
  • remove bump from rumpus/alfresco wall, and unusual bump in ceiling in family room.
  • Fix ceiling in alfresco where paint damaged by brick acid wash.
  • Flashing at alfresco will be cut down.
  • Bricks to be replaced at alfresco window (last 2 are raised). Also at alfresco pillar where they incorrectly drilled a hole to pull wire through and at the study pillar where a faulty brick was laid.
  • Garage door needs to be repaired where someone has tried to break in.
  • Study door needs to be repaired the bottom has a chip in it.
  • Bed 2 wall damaged.
  • Bed 4 wardrobe no handles
  • Front door handel to be changed should be antique brass. SS has ordered a brass deadlock and will put it on our garage.
  • Alfresco door damaged will be replaced.
At final inspection.
  • Touch up walls, eves and ceilings.
  • Provide 4 extra handles 2 for laundry 2 for pantry.
  • Caulk the basins with white not the clear silicone.

The electrician was also on site today and we asked if we could make the few little changes and they have agreed. We are getting a low voltage light installed at the poritco and one above each basin in the ensuite. We have lowered at the junction box at the front pillar of the master bedroom to use it for garden lights.

Monday, June 1, 2009

Moving things along........



We are finally seeing things pick up pace on site. The data cable self confessed genius has been back and has installed the alarm although we can't make out if he has put the correct sensors in. All the data cables have been pulled out of the walls.

The Mirrors have been installed, the main bathroom one is slightly off center but we will get over it. The ensuite is a lot brighter with the mirror now installed but we have decided to add two extra low voltage down lights, one over each basin.

The down pipes are all getting connected.

Friday, May 29, 2009

Bricks cleaned.

The bricks that have been cleaned and the mortar is a very good match which was a concerns with them having to be relaid. We still think that some rows are not straight at the left garage pillar and they have not touched the right pillar at all. The portico pillar is now fine. We will have to talk to SS.

Thursday, May 28, 2009

Straightening walls

The plasterer is back at the site. He is fixing the wall that is bowed in the kitchen that backs on to the linen cupboard and also the rumpus and family room wall that is not plumb. I noticed that the games room wall that is still not plumb has not been fixed I will have to talk to SS. He has also finished the cornice in the kitchen which is a wasted effort as we are still waiting for the top cabinets to be replaced and a bulkhead to go in. Oh well at least it is better sealed for us.

There is a hold up on the kitchen cabinets as someone forgot to put the order through. Once the kitchen cabinets do arrive, we have decided that we are changing where the existing cabinets will go. We are still having one unit transferred to the laundry but we are now putting the other one in the pantry above the sink.

We are meeting SS out on site Tuesday to go through the list of outstanding items.

Tuesday, May 26, 2009

Carpenter is back.


The carpenter is back on site and has replace the two vertical arcs at the rear wall of the garage with one whole mdf board and it has improved the way it looks but is still suspect at the top, something is just not quite right here. He has also put small quads at the alfresco and frankly they look crap! The finish where the alfresco beams meet the bricks is just a plain eyesore and is just not acceptable. It does not look crap at the display home and we will not accept this at all. We will have to talk to SS.

Saturday, May 23, 2009

We have a back fence!


Our neighbour behind us has moved in and they already have fences around their block! We were very surprised as we thought it would take ages for the developer to authorize the fences since they are paying for them........yep our fences are included in the price of the block!

It was great to get an idea of the size of the back yard now that the back fence is up. The blocks on our side are bigger and also wider so the fences do not match up so we are still missing part of our back fence. I thought it was going to look smaller but it is ample space for our boys to play in without being too much work for us. We rather spend time with them rather than maintaining a backyard for them. We have two parks at the end of our street so we will enjoy those while someone else does the watering and cutting of the grass!

Friday, May 22, 2009

Bricks have been relaid.




Bricks have been relaid at the left wall of the garage and the left front pillar to the portico where the were originally laid on a slant. The front step and back window sill have been relaid without a split brick and look a heck of a lot better. The front door and door frame have also been sanded ready to be stained. They have also relaid the bricks at the toilet window to center it in the middle of the wall.

Tuesday, May 19, 2009

A little progress



The shower screens have been installed in both the bathroom and ensuite. We can't get in to take photos and we could on just see them through the obscured windows.

We have now been in so here are the photos. Update 2/6.

Monday, May 18, 2009

Waiting........waiting.......waiting.....................

I rang SS for an update on our construction today. He informed me that he is waiting for trades people to finish on other sites so that they can come back to ours. I mentioned our bricks are walking off site and he said he has already ordered more bricks to replace the bricks that will have to be removed and relaid. I requested that the left over pallet from the first batch be used for the front as I do not want any colour variances. He said that he expects the bricklayer back on site Thursday.

Friday, May 15, 2009

Not much happening around here!!!


I rang SS yesterday to arrange to view the house and he said a chippy would be next door to open up. When I arrived on site only the site cleaners were there and they don't have master keys so no-one was around to open up, Grrrrrrr.

The alfresco door has been stained but from what I could tell nothing else had been done all week. I will call SS Monday and find out what is going on and why the progress has stalled.

The site cleaners were good they asked if I wanted the side of our block leveled and if I wanted next doors roof tiles removed from our property. I gave them the thumbs up and all was done in a jiffy. Good on'ya cleaning Bob's.

More bricks have walked..........

Friday, May 8, 2009

Attending to the issues.

The stone bench has been has been cut again to fit the sink in as the hole cut at the factory was too small. They obviously cut to what is standard or missed that we upgraded our sink to have two large bowls rather than one and a half. Needless to say we are not too thrilled about the fine dust that is now all over the walls and everywhere else.

Spoke to SS who is now back from leave, he said that the master window has been fixed and he will have photos of the work forwarded to us.

Our bricks are beginning to walk off site, as soon as the bricklaying has been completed we are going to remove the remaining bricks ourselves before they all disappear.

Wednesday, May 6, 2009

More tiling and grout.





The tiling to the niche and splashback in the ensuite as well as the shower base of the main bathroom have all been completed and grouted. The only tiling that remains is at the rangehood when the cupboards finally get replaced.

I noticed damage to the wall backing on to the ensuite was damaged in bedroom 2. The plaster will have to be fixed and repainted.

Monday, May 4, 2009

Spare tiles left over.

I spoke to the Tiler today, he has been very economical and has not needed to use the extra box of feature tiles I supplied. He said I can come out on site Wednesday to pick up any of the extra tiles left over so they don't walk of site and he will get his apprentice to load them up in my car. What a cool guy!

Friday, May 1, 2009

More tiling and we have rollerdoors

I spoke to the tiler today he said that he has finished the ensuite shower walls, the tiling to the bathroom vanity and the grouting was done in the main bathroom as well as the laundry for the 100x300 cream tiles. He only has the niche and splashback to tile in the ensuite, the shower base of the main bathroom as well as the tiling at the rangehood when the cupboards finally get replaced.

The rollerdoors were put up today, the front rollerdoor is huge!

I trust you all love my new car!

Thursday, April 30, 2009

More tiling

The tile layer completed tiling the bath in the main bathroom, the shower base in the ensuite and added two extra tiles to the kitchen today. He is unable to tile the remaining tiles to the kitchen wall until the top cupboards are replaced.
I also spoke to him today regarding the ensuite shower tile laying. On the tile plan we originally chose to have vertical brick bond tiling to the shower walls with the metalic rust 300x600 tiles. We are tiling the spa ourselves and there will only be one row of tiles on the face and one row for the splashback. I explained that I thought it would look crappy if we cut every second tile in half at the spa to get a brickbond effect and if we tiled the spa tiles straight the shower would not match, he totally agreed. I therefore requested for him to tile the shower vertical stacked but not brickbond.

I spoke to Man in charge while SS is in holidays to approve the changes and he said no probs. I copied the drawings wrote the changes on them and then delivered them to site. I wanted to avoid confusion and to back the tile layer up so that he does not get wrapped over the knuckles for making changes.

Wednesday, April 29, 2009

We have some catching up to do.

Hi everyone,

As it always seems to go with volume builders our construction ran off course. The last few weeks have been a bit of a nightmare and not what we expected from Porter Davis Homes. We are hoping that over the next few weeks things will get back on track and that by the time we get to handover that both our home and faith will be restored.

The last time I updated it was the 3/4 and even then I was behind on photos. I will try and get up to date with my notes today and get a start on the photos too. So stay tuned the updates are coming.

Tuesday, April 28, 2009

Tiler on site.

I met the tile layer on site today and explained that I want to continue tiling up to the ceiling behind the rangehood in the kitchen and that I also want the same tiles for the splashback in the main bathroom. I had discussed this with head honcho at the meeting on Friday and he said no problem meet tile layer on site and work it out with him.

The tiler was really helpful. He explained about the sharp edge we would get once the tiles were cut for the main bathroom splashback. He advised to lay only two rows up rather than three which would put the sharp edge of the tile on the to the vanity bench and where the mirror would meet. Once these edges get caulked it would no longer be a problem. I agreed and gave him the go ahead. I left him one of the extra boxes of tiles I had purchased.

The tiling completed today was the laundry splashback,shower walls and top area surrounding the bath in the main bathroom.............................................and the kitchen splashback.
The screeding was also completed to both shower bases.
The basins were also installed today.

Monday, April 27, 2009

Carpet change.

We found out on Friday that we are about 6 weeks away from completion which is way ahead of schedule. I rang the carpet place to see if they had ordered the carpet in and they said they need to come out and do a measure before to order the Navy Miracle twist in. They rang the manufacturer and found that it would take 8 weeks. Eeeeeeeeek They asked if I could come in because they had a fair amount of new stock and I might be able to switch to something in stock.

I dropped our boys off to my friend Janine's house and then went to the carpet place. It was so wonderful to go there on my own. I was able to take my time and decide what I wanted rather rush because one of my boys was causing a disaster. Janine if you read this you made my day, thank you!

I found a navy carpet that was far better quality, half the price of the original one I chose and in stock which took care of the boys rooms. We decided to change the carpet of the spare room to the same colour as the master bedroom being the fawn coloured "interior charm." We also changed our minds about having navy in the home theatre as it clashed with the colours in the kitchen. So I chose a donkey brown colour and liked it so much that I got an extra piece as a rug for the family room. In the end I saved $300 and also got two extra 2x2.5m rugs out of an off cut which we can use under our desks. The $300 we saved will pay for the over locking of the rugs.

We are really happy to not have to wait for our carpet, when you add up the savings and extra rugs we get on top, today was a really good day!

Friday, April 24, 2009

Meeting on site.

We met the construction "head honcho" and branch manger from PD Keilor Park out on site today to go through our independent inspectors report. We felt that we were listened too, that we got the chance to express why we lost trust in PD and felt the need to escalate to head office. We stated our disappointment in the quality of workmanship from some of the trades. We also explained our dissatisfaction of the way that our issues have been handled to date.

Once we started pointing out everything on the report as well as the other issues we had including the kitchen wall that is bowed and the flashing missing from the laundry door frame. They realised our complaints were legitimate and that we were not just going on about nothing.

They took down notes and said that they will fix everything on the report plus the other things that we were not happy with. Time will tell if they act on these things and restore our faith. In the meantime we will continue to hold payment to enforce that it does all happen.

Now for the kitchen bench saga.........we were mislead regarding the edge finish and the manufacturer does not provide a full rounded edge including the face to the stone bench. They showed us a booklet with the edge finishes they do provide and in the end we settled to keep the existing one. It's not what I wanted but in the end I can live with it and will have to get over it.

The bath waterproofing issue. The bath and shower areas had been waterproofed. we took photos to show Dad and explained to him what they had done, he believes it may do the job but urged us to keep an eye on it. In Dad's opinion this window should be raised and is poorly designed, I agree and think who ever designed this doesn't have kids!


Tuesday, April 21, 2009

Tile issue resolved.

I arrived on site today to meet with the Sales Rep from National Tiles and was bailed up by the painter saying I needed permission to be there. I growled back at him saying that I had spoken to Probie and wouldn't be there without asking permission, so he backed off.

The feature tiles delivered on site were incorrect. Four out of the six boxes were the correct tile, however two boxes as well as the one extra tile that was on top were the incorrect colour. The rep from National tiles removed the two incorrect boxes and extra tile, he noted the batch numbers of the correct tiles on site and will replace them with the same tiles from the same batch. I email Probie to let SS know so that he does not think tiles have been stolen from site.

I had a look around and noticed that the flashing is also missing on the back laundry door, they will have to take this frame out too. Grrrrrrrrrrrrr

The painter was repainting the wall that was on the inspectors report so they must be starting to fix the substandard work.

Monday, April 20, 2009

Meeting postponed and yet another mistake on site.

I rang this morning to see if Construction head honcho coming on site he can not make it, we have rescheduled for Friday. There was no point in meeting the Keilor Park branch staff out on site as we did not feel they would address the issues adequately or take us seriously.

We went out again to check what is going on with the master window but nothing has happened. We have noticed a dent in the frame of the dining room window on the external wall.

We also saw the tiles are on site and guess what? Yep you guess it, the wrong tiles are on site, unbelievable!

Friday, April 17, 2009

Extra tiles for kitchen and spa

I rang National Tiles today because I purchased extra (Metalic Rust) tiles from another branch of Nat Tiles and wanted to make sure I had the same batch colour as the one that PD are laying. We want to extend the tiling to the kitchen splashback right up to the ceiling behind the rangehood. We also need extra tiles for the spa bath we are installing ourselves as we are laying these in our ensuite shower.

The lovely bright spark I spoke to at National tiles Port Melb today rang me back with an hour and confirmed that we had the same batch, issue resolved.

We have your attention!

I got a call first thing this morning from head office and feel like I have finally been heard. This manager was apologetic and proactive in wanting to get things resolved. She is trying to arrange for a construction head honcho to meet us out on site Monday.

We went out again today and found that the bricks have been removed from the front master bedroom window edge sill. What are they up to now? We know that the window appears to be set too high and needs to be dropped, but now we now have the two windows at the front with different brick laying, the study has split bricks and the master does not?



Thursday, April 16, 2009

Enough is enough!

We are now annoyed at the number of mistakes as well as the lack of response to our inspectors report. We have escalated our concerns to management at PD Keilor Park. We feel that we are constantly pointing out things needing to be fixed and nothing is happening to rectify them. We are no longer prepared to accept "it all gets fixed in then end".

Management at PD Keilor park passed our concerns off to an assistant, in our eyes this branch makes no apology for the substandard work performed on site and is not taking our concerns seriously.

We have now escalated our issues to head office. We are continuing to hold payment for the fixing invoice and do not intend to make any further payments until all items big and small are fixed. We do not want to end up in dispute with PD we just want our house built to the standard of the display home and to date that is not what we are getting.

Wednesday, April 15, 2009

Painting finished and stone bench in.


The painting has finished and all the window protection has been removed so we can see inside again. We are fairly happy with the painting but will reserve judgment until it we inspect it with proper lighting. We have seen a few areas which need attention but they are more to do with the plastering than the paint job.

The kitchen stone bench has been fitted and has the wrong finish on the edge. Also where the return meets up with the wall the have caulked a joint and the gap does not run straight. From what I can tell it is due to the wall having a bow in it. Why am I still picking up walls that are out? Honestly this is getting ridiculous. We are as frustrated by the poor workmanship as we are with the number of mistakes being made.

Monday, April 13, 2009

Internal painting.


We drove out today "Easter Monday" wondering if anyone will be on site. When we arrived we found the painter was working so we got to see the inside of the house. We are really happy with the colour we chose it is warm and sunny just what we were after. The colour of the walls is 1/4 strength Spun Toffee, the colour for the architraves and doors is porcelain. The photo makes it look a lot more yellow than it really is.

The ceiling and cornices were already finished, as were all the doors and architraves. The painter was still painting some of the walls and had just started the garage.

We were never asked at Hopetoun what colour we wanted in the garage and it gets assumed that is part of the internal painted walls. Looking at it now I would have preferred it to be the paperbark colour to match the external painting but is not a big enough concern to want to change it, so no big deal.

Tuesday, April 7, 2009

Our Inspectors report.

We received our own independent building inspectors report and we are not pleased with the number of issues that need to be fixed. We are so relieved that we hired him as he has now confirmed that the issues we have are legitimate.
We have several items and naturally the major ones are our biggest concern. These include plaster needing to come down so that a frame that was cut and "fudged" can be rebuilt to meet the standards. The front door as well as alfresco frames that we felt were not level now have to be removed and refitted because the flashing is missing underneath them both. Sections of brick wall also have to be relaid because they have not been laid straight which is very disappointing. The garage and front fascia needs to be replaced as does the guttering over the portico because it is damaged or poorly fitted. All the quads at the front of the house are out of level. We have forwarded a copy of the Building inspectors report to PD and has stated that we are holding payment on the current invoice. Probie has passed it on to be addressed.
We started out so well and now ..........Hmmmmmmmmm.........NOT HAPPY!

Monday, April 6, 2009

Ready.... set..... paint!

The painter has arrived on site. He has commenced the external painting and has painted the front eves, alfresco ceiling, quads and lintels.

He has also prepared the internal of the house for painting, all the windows have been covered in so that the paint does not pray on to them.

Friday, April 3, 2009

Pipes & panels



The hot water solar panel has been installed and the pipes have been run to the ensuite, I hope they will be finished off a little better than they have been. They have removed half a brick and the pipes are hanging out, they may just mortar around it which is not the finish I was expecting. I would have expected them to put proper fitting like the other pipes. I will speak to SS.



The colorbond down pipes have been installed and we are really happy with the colour of them as they seem to disappear rather than stand out. The colour we chose was jasper which is the same as the gutters. The back rollerdoor to the garage will also be the same colour.

Thursday, April 2, 2009

More holes!!!!!



We went through our photos and asked our inspector if could check the wall with a probe where we believe there is still insulation missing. He advised us to meet SS out on site and have him cut holes as it would be easier to patch up now rather than later when walls have been painted.

So I met SS out on site today to cut holes in the plaster and found another 10 out of the 12 spots were missing insulation. Larger holes will now be cut and insulation will get stuffed in. This is frankly very disappointing considering we asked the question and were told that it was in the walls. Between this issue, the master bedroom window and the poor BSS report we are fast loosing faith in PD.

The bath has been delivered and installed, there was heaps of room for it to be lowered but it is too late now. I will request that I have something in writing explaining how they intend to waterproof to prevent water seeping into the frame below at the window.

Wednesday, April 1, 2009

Kitchen update

Next time check, check and check again!

The plans for the kitchen were wrong on the final drawings. The floor plan was correct but the elevation was incorrect. That is why we ended up with four door cupboards instead of three doors either side of the rangehood. My original administrator Madam X called and confessed that she did recall us asking for 3 doors. I was pleased that she was honest enough to say I buggered up.

What has been negotiated.......
We will pay cost price for the new correct cabinets to be made.
PD will pay to take the incorrect cabinets down and relocate them to the laundry. Also they will cover the cost to put the new cabinets up. PD will also have the cupboard doors above the fridge changed to a single door as per the drawings.

Tuesday, March 31, 2009

Garage walls



The walls of the garage have had the plastered and the cornices put up. It looks so much bigger now.

Monday, March 30, 2009

Bricks cleaned.


The bricks have been acid washed and look fantastic. It is a shame that the same can not be said about the bricklaying. Some of the bricks on the front walls either side of the garage look like they are not level and the front pillar is even worse. This is the front of the home and we do not feel it is up to the standard we expect from Porter Davis, most disappointing. We have contacted our inspector to come back and check it. There are a few bricks that have chips and we want them replaced.

We had settlement on our home today so we now have one less mortgage fweeeew. We were lucky to have the opportunity to stay on in our home and don't have to move out until November. We have plenty of time up our sleeves to slowly pack and even when we move we can take our time. The fact that we did not have to move twice was a real blessing.

Friday, March 27, 2009

Clean up

Site clean done again.

Thursday, March 26, 2009

We got our own inspector in.

We organised our own independent inspector to come out and inspect the work to date. We particularly wanted him to check how the bedroom window has been installed because it appears it is not sitting on the frame but rather propped up on some packing. It looks like the frame has been cut and fudged. Here take a look for your self.

We are unhappy with our toilet window that is not in the middle of the wall and it is obvious. We are also still concerned with some of the brick laying, our inspector will come back and check it when the bricks have been cleaned.

The plaster for the garage has been delivered so I guess that will get done next.

Wednesday, March 25, 2009

Plastering continues

Plasterer returned to patch and sand walls marked by inspector to be fixed. He was going to install cornices in the kitchen until I told him that the kitchen cupboards were going to be replaced and that the new cupboards will have bulkheads.

I found the BSS inspectors report and I am not impressed! I not happy with the lack of progress in fixing the things that I have brought to the attention of SS either. We are noticing more suspect quality work every time we come out and now feel it necessary to get our own independent inspector in.

Monday, March 23, 2009

Work on the garage



The temporary timber frame at the front of the garage has been removed, now that the steel lintel is holding the roof up over the wide opening for the rollerdoor.

The roof tiles have been removed for the box gutter to be installed near the parapet wall.

Friday, March 20, 2009

Site inspection.

The BSS independent inspector came out on site we can see the report on the kitchen bench.

Wednesday, March 18, 2009

Third time lucky


The cables at the pillars in the alfresco have now been pulled out in the correct spot. The holes in the mortar will need to be filled and the bricks that were drilled into will need to replaced.

Tuesday, March 17, 2009

Kitchen, laundry & Bathrooms take shape.







The Kitchen has been installed and looks fantastic we are thrilled about the layout and the colour. There has been mistakes made though. The top kitchen cabinets either side of the range hood are wrong, there should be three doors either side not four. They were also installed at the wrong height 700mm from the bottom bench and should be should be 600mm. The cupboard above the fridge is also incorrect there should be one door and there are two. I will have to speak to probie.

The laundry cabinet as well as the vanities have also been installed in the Bathroom and ensuite, again we are really happy with the colours we have chosen.
The laundry stainless steel sink which was an upgrade has been installed, all the other sinks have been delivered and are waiting to be installed.

The eves at the front facade have now all been covered in it is a shame that the quads are all not level!

They have moved the electrical cables from the inside of the brick pillars in the alfresco to the outer side which is correct, unfortunately they have now been pulled out at the top instead of the bottom!!! It will have to be third time lucky.