The plaster is up on all the walls and all the ceilings in every room. The bulkhead has gone up in the entrance. The plaster Bobs did put up the insulation before the plaster, they used new insulation because the one on the floor had glass through it from the smashed window. The plasterboards have all been joined together and all the nail holes plastered over. I guess they will be putting up the cornices next.
The only area not completed is the garage because we are waiting on the lintel which is holding up the brickwork and the garage door that would stop rain blowing into the garage on the plaster.
Site superman went through all our issues with me and they are all either sorted or he is working on it. So it is all good.
We have had a site clean they have removed all the rubbish from the back yard and the side of the house near the alfresco.
We have stacked up some bricks and roof tiles on a pallet to keep in the back yard.